Project Update: Light at the End of the Tunnel

Posted on October 11, 2016 at 9:13 AM by Travis Elliott


Logo

Project Update:
 Friday, October 7

Paving is Complete:
The main roundabout at Brush Creek and Wood Road is nearing completion, and crews finished installing the final lift of asphalt this week. Lane stripes were also added, and we are now awaiting the new down-valley bus stop shelter and guard rail. Congratulations to all of the hard working crews on reaching this major milestone.

The project will be complete by the end of October.

Mini Roundabout Installations:
The long awaited mini roundabout construction has begun and will be complete by October 17th, if Mother Nature cooperates. A special type of concrete is being used for the project allowing a compact construction schedule. Bus routes will return to the transit center following the mini roundabout completion.  

Photos:
Mini medians 
Crews installed the first of the mini-roundabout medians on Friday.
Hydro Excavation 
Hydro excavation was used to install utilities and conduits for the street lights. 

Check out the latest images and videos on the project website, Project Images

Additional Information:

Construction Hours:
Monday - Saturday
7:00am - 6:00pm

Project Hotline and Contacts:


Comments